Time and Work: Techniques and examples with solutions Today I'm going to discuss a very important topic i.e. Time and Work of quantitative aptitude. I

Bergen 2020-11-22 Answered
Time and Work: Techniques and examples with solutionsToday I'm going to discuss a very important topic i.e. Time and Work of quantitative aptitude. In almost every exam at least 2-3 question are asked every time. In this chapter, I will tell you about a definite relationship between Time and work and easy method to solve the problems.
You can still ask an expert for help

Expert Community at Your Service

  • Live experts 24/7
  • Questions are typically answered in as fast as 30 minutes
  • Personalized clear answers
Learn more

Solve your problem for the price of one coffee

  • Available 24/7
  • Math expert for every subject
  • Pay only if we can solve it
Ask Question

Expert Answer

question2answer
Answered 2021-04-21 Author has 162 answers

Three main factors of Time and Work

There is a definite relationship between Time and Work. In this concept, there are only three factors:

  • Time taken to complete a certain job
  • Unit of work done
  • Number of persons doing the job

There is a fundamental relationship between these three, discussed as follows:

Work done(W) = Number of days(Time taken)(T or D) times Number of men(M)

W=D×M

Some basic points

More number of men can do more work i.e. both are directly proportional
More number of men take less time to complete certain job i.e. both are inversely proportional

By summarizing, we get

(W1)(W2)=((M1)(M2))×((D1)(D2))            

Lets start solving some examples:

Example1: 10 men can cut 8trees in 16 days. In how many days can 6men cut 10trees?

Solution: This is a very simple example. You are given:

W1=8
W2=10
M1=10
M2=6
M2=6
D2=?

Using formula,

(W1)(W2)=((M1)(M2))×((D1)(D2))

8(10)=106×(16)(D2)
D2=33.3

Concept of efficiency

This means, "How much work one person can do in one day (expressed in percentage)"
For example: A person can do a job in 2days He can do 50% work in one day Therefore, his efficiency will be 50%

Just a 2-step concept

This concept involves two steps to calculate efficiency:

  • Convert into fraction i.e. per day work
  • Multiply with 100 i.e. convert into percentage

Try the following example first, then re-read above points

Example2: If a person can complete his work in 5 days. What will be his efficiency?

Solution: Number of days a person take to complete his work = 5

He is doing 15 th work per day  (converted into fraction)

Convert it into percentage:

1005=20%

Therefore, his efficiency is 20%.

Summarizing, If a person can do his job in n days, efficiency will be

Efficiency =100n%

Note: Negative efficiency cancels the positive efficiency

For Example: Positive efficiency =5% Negative efficiency =1.5% Net efficiency =51.5=3.5% 
As we all know, in competitive exams time management is very important. I suggest you to learn the fractions till 15.
 

Number of days required to complete work Work/Day Efficiency (%)
N 1n 100n
1 1 100
2 12 50
3 13 33.33
4 14 25
5 15 20
6 16 16.66
7 17 14.28
8 18 12.5
9 19 11.11
10 110 10
11 111 9.09
12 112 8.33
13 113 7.69
14 114 7.14
15 115 6.66


Example3: A can do a job in 10 days. B can do a job in 5 days. In how many days they can complete the job if they work together?

Solution: Consider the above table

A's efficiency =10%((100)(10))
B's efficiency =20%

A+ B efficiency =10+20=30%
This means, In one day A and B together can do 30% of work.

Therefore,Number of days A and B together take to do 100% of work =(100)(30)

3.33 days

Example4: A and B together can do a job in 4 days. If A can do job in 12 days if he works alone, then how many days B alone take to complete the job?

Solution: A+B take = 4 days

A+Bs efficiency =25% i.e. they together do 25% of work in one day

A takes = 12 days
A's efficiency = 8.33%

B's efficiency =(A+B)(A)

25%8.33%=16.66%

This means, B can do 16.66% work in one day
Therefore, to complete the job he will take =(100)(16.66) days
  6days

Example5: A and B can do job in 8 days. B and C can do same job in 12 days. A, B and C together can do same job in 6 days. In how many days A and C together can complete the job?

Solution: You are given that:

A+B's efficiency =12.5%
B+C's efficiency =8.33%
A+B+C's efficiency =16.66%

we need to find A+C

Consider, 2(A+B+C)=(A+B)+(B+C)+(C+A)
2(16.66)=12.5+8.33+(C+A)
C+A=12.49=12.5
Therefore, A and C takes=(100)(12.5)=8 days

Hope you all understand this topic. I will soon update questions for your practice.

Not exactly what you’re looking for?
Ask My Question

Expert Community at Your Service

  • Live experts 24/7
  • Questions are typically answered in as fast as 30 minutes
  • Personalized clear answers
Learn more

Relevant Questions

asked 2022-05-27
How do you find the mean of 26, 25, 24, 28?
asked 2022-04-26
Given a set {-3, x,3,4,6,5, -3, 2}, for what x would the mean of the set be -1?
asked 2022-04-24
Given a set {-1, 2, -12,52,x}, for what x would the mean of the set be -3?
asked 2021-08-12
Refer to the Journal of Applied Psychology (Jan. 2011) study of the determinants of task performance. In addition to x1 = conscientiousness score and x2 = {1 if highly complex job, 0 if not}, the researchers also used x3 = emotional stability score, x4 = organizational citizenship behavior score, and x5 = counterproductive work behavior score to model y = task performance score. One of their concerns is the level of multicollinearity in the data. A matrix of correlations for all possible pairs of independent variables follows. Based on this information, do you detect a moderate or high level of multicollinearity? If so, what are your recommendations? x1 x2 x3 x4 Conscientiousness (x1) Job Complexity (x2).13 Emotional Stability (x3).62.14 Organizational Citizenship (x4).24.03.24 Counterproductive Work (x5)-.23-.23-.02-.62
asked 2022-04-25
Given a set {4, -2, -12, 5, x}, for what x would the mean of the set be -5?
asked 2022-03-16
Andy has grades of 84, 65 and 76 on three math tests. What grade must he obtain on the next test to have an average of exactly 80 for the four tests?
asked 2020-10-21
Explain which measure of spread would best describe the payroll:the range,the IQR, or the standard deviation.